ACI Global Home Middle East Region Portal Western Europe Region Portal
Email Address is required Invalid Email Address
In today’s market, it is imperative to be knowledgeable and have an edge over the competition. ACI members have it…they are engaged, informed, and stay up to date by taking advantage of benefits that ACI membership provides them.
Read more about membership
Learn More
Become an ACI Member
Topics In Concrete
Home > Frequently Asked Questions
In This Section
Frequently Asked Questions
Submit a Question
Search other resources on the ACI website for answers to technical questions
Q. When can the finishing procedure be started? A. The finishing procedure should be started as soon as possible after bleeding has stopped and the concrete has stiffened to a degree that the surface does not close upon texturing. This typically coincides with the time of initial setting of concrete. Finishing needs to be completed before the time of final setting of concrete. References: SP-1(02); ACI 302.1R-15; CCS-5(16); ACI 304R-00 Topics in Concrete: Concrete Fundamentals; Pavement; Placing; Slab
Q. When can the finishing procedure be started?
A. The finishing procedure should be started as soon as possible after bleeding has stopped and the concrete has stiffened to a degree that the surface does not close upon texturing. This typically coincides with the time of initial setting of concrete. Finishing needs to be completed before the time of final setting of concrete.
References: SP-1(02); ACI 302.1R-15; CCS-5(16); ACI 304R-00
Topics in Concrete: Concrete Fundamentals; Pavement; Placing; Slab