Title: Foundation and steel and concrete structures in the Torre de Cristal. A high-rise building process

Author(s): Viñals Millán, J. I.; Ruiz Ocaña de Pascual, Á.; Peigneux Llorca, J. R.

Publication: ACHE

Volume: 59

Issue: 249

Appears on pages(s): 89 - 106

Keywords: Slipform, tower crane, composite column, hollow-core unit, self-compacting concrete.

DOI:

Date: 1/5/2008

Abstract:
Construction began on the structure of the Glass Tower on 10 March 2005, with an estimated completion period of 24 months. With the deep foundations finished and the basements excavated in this large and necessarily complex project in terms of the number of activities to be coordinated, this new stage of construction entailed the added difficulty of working at considerable heights. In order to complete the works on schedule, provision was made for the on-site resources required and action was taken to develop the building process described in the following sections, to ensure successful conclusion of the project. The unique characteristics of the curtain wall assembly scheme, the survey control systems and the high-strength self-compacting concrete 100 MPa used at the base of the tower supports are described at the end of the article.


ACI International Partner, ACHE Spain, International Partner Access

View Resource »  



  


ABOUT THE INTERNATIONAL CONCRETE ABSTRACTS PORTAL

  • The International Concrete Abstracts Portal is an ACI led collaboration with leading technical organizations from within the international concrete industry and offers the most comprehensive collection of published concrete abstracts.